單項選擇題An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?

A.Total float for the activity is 9 days.
B.The early finish date ofthe activity is the end ofthe day on the 14th.
C.The late finish date is the 25th.
D.The activity can be completed in 2 days ifthe resources devoted to it are doubled.


你可能感興趣的試題

4.單項選擇題

Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()

A.executive IT manager
B.projectmanger
C.change control board
D.projectsponsor

6.單項選擇題

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

A.activity duration estimating, schedule developing, activity resource estimating
B.activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating

7.單項選擇題

The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.

A.subdividing
B.assessing
C.planning
D.integrating