單項選擇題

The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

A.Planning
B.Executing
C.Monitoring and Controlling
D.Closing


你可能感興趣的試題

1.單項選擇題

The()defines the phases that connect the beginning of a project to its end.

A.schedule
B.project life cycle
C.temporary
D.milestone

2.單項選擇題

()means that every project has a definite beginning and a definite end.

A.Projectphase
B.Unique
C.Temporary
D.Closure

6.單項選擇題

 The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.

A.costaggregation
B.reserve analysis
C.parametricestimating
D.funding limit reconciliation